In this subchapter:
((1)) ** Agency** The term “agency” has the meaning given the term in .section 551 of title 5
((2)) ** Agency CERPO** The term “agency CERPO” means the chief environmental review and permitting officer of an agency, as designated by the head of the agency under .section 4370m–1(b)(2)(A)(iii)(I) of this title
((3)) ** Authorization** The term “authorization” means any license, permit, approval, finding, determination, or other administrative decision issued by an agency and any interagency consultation that is required or authorized under Federal law in order to site, construct, reconstruct, or commence operations of a covered project administered by a Federal agency or, in the case of a State that chooses to participate in the environmental review and authorization process in accordance with , a State agency.section 4370m–2(c)(3)(A) of this title
((4)) ** Cooperating agency** The term “cooperating agency” has the meaning given the term in section 1508.1 of title 40, Code of Federal Regulations (or successor regulations).
((5)) ** Council** The term “Council” means the Federal Permitting Improvement Steering Council established under .section 4370m–1(a) of this title
((6)) ** Covered project**
((A)) ** In general** The term “covered project” means any activity in the United States that requires authorization or environmental review by a Federal agency involving construction of infrastructure for renewable or conventional energy production, electricity transmission, surface transportation, aviation, ports and waterways, water resource projects, broadband, pipelines, manufacturing, semiconductors, artificial intelligence and machine learning, high-performance computing and advanced computer hardware and software, quantum information science and technology, data storage and data management, cybersecurity, carbon capture, energy storage, or any other sector as determined by a majority vote of the Council that—
((i))
((I)) is subject to NEPA;
((II)) is likely to require a total investment of more than $200,000,000; and
((III)) does not qualify for abbreviated authorization or environmental review processes under any applicable law;
((ii)) is covered by a programmatic plan or environmental review developed for the primary purpose of facilitating development of carbon dioxide pipelines;
((iii)) is—
((I)) subject to NEPA;
((II)) sponsored by an Indian Tribe (as defined in ), an Alaska Native Corporation, a Native Hawaiian organization (as defined in ), the Department of Hawaiian Home Lands, or the Office of Hawaiian Affairs; and
((III)) located on land owned or under the jurisdiction of the entity that sponsors the activity under subclause (II); or
((iv)) is subject to NEPA and the size and complexity of which, in the opinion of the Council, make the project likely to benefit from enhanced oversight and coordination, including a project likely to require—
((I)) authorization from or environmental review involving more than 2 Federal agencies; or
((II)) the preparation of an environmental impact statement under NEPA.
((B)) ** Exclusion** The term “covered project” does not include—
((i)) any project subject to ; or
((ii)) any project subject to .
((C)) ** Inclusion** For purposes of subparagraph (A), construction of infrastructure for carbon capture includes construction of—
((i)) any facility, technology, or system that captures, utilizes, or sequesters carbon dioxide emissions, including projects for direct air capture (as defined in paragraph (6)(B)(i) of ); and
((ii)) carbon dioxide pipelines.
((7)) ** Dashboard** The term “Dashboard” means the Permitting Dashboard required under .section 4370m–2(b) of this title
((8)) ** Environmental assessment** The term “environmental assessment” has the meaning given the term in section 1508.1 of title 40, Code of Federal Regulations (or successor regulations).
((9)) ** Environmental document**
((A)) ** In general** The term “environmental document” means an environmental assessment, finding of no significant impact, notice of intent, environmental impact statement, or record of decision.
((B)) ** Inclusions** The term “environmental document” includes—
((i)) any document that is a supplement to a document described in subparagraph (A); and
((ii)) a document prepared pursuant to a court order.
((10)) ** Environmental impact statement** The term “environmental impact statement” means the detailed written statement required under section 102(2)(C) of NEPA [].42 U.S.C. 4332(2)(C)
((11)) ** Environmental review** The term “environmental review” means the agency procedures and processes for applying a categorical exclusion or for preparing an environmental assessment, an environmental impact statement, or other document required under NEPA.
((12)) ** Executive Director** The term “Executive Director” means the Executive Director appointed by the President under .section 4370m–1(b)(1)(A) of this title
((13)) ** Facilitating agency** The term “facilitating agency” means the agency that receives the initial notification from the project sponsor required under .section 4370m–2(a) of this title
((14)) ** Inventory** The term “inventory” means the inventory of covered projects established by the Executive Director under .section 4370m–1(c)(1)(A) of this title
((15)) ** Lead agency** The term “lead agency” means the agency with principal responsibility for an environmental review of a covered project under NEPA and parts 1500 through 1508 of title 40, Code of Federal Regulations (or successor regulations).
((16)) ** NEPA** The term “NEPA” means the National Environmental Policy Act of 1969 ( et seq.).42 U.S.C. 4321
((17)) ** Participating agency** The term “participating agency” means an agency participating in an environmental review or authorization for a covered project in accordance with .section 4370m–2 of this title
((18)) ** Project sponsor** The term “project sponsor” means an entity, including any private, public, or public-private entity, seeking an authorization for a covered project.