Senator · R-UT
The bill trades substantially faster, more predictable permitting and reduced federal procedural burdens for dredging and port projects against reduced federal environmental oversight, compressed review timelines, and increased risk that vulnerable communities and waterways will bear the consequences of weaker protections.
Port operators, dredging contractors, and other project sponsors get faster, more predictable permitting — a single nationwide permit with NEPA completed within 2 years, a 10-year NWP term, 30-day decision deadlines, and deemed approvals for missed deadlines accelerates projects and reduces uncertainty.
State certifying authorities and applicants face clearer, faster §401 processes — agencies must determine completeness within 14 days and act on complete certifications within one year, reducing procedural delays for state review and permit issuance.
Project sponsors see reduced duplicative permitting — compliance with CWA §404 and §408 can be deemed to satisfy Rivers and Harbors Act §14(a), lowering paperwork and streamlining approvals.
Local communities and waterways face greater environmental risk because limits on EPA's §404(c) authority and restrictions on considering alternatives reduce federal oversight over disposal sites and protective options.
Homeowners, rural communities, and ecosystems may be harmed because 'deemed approvals' when agencies miss deadlines let projects proceed without full review or mitigation.
Compressed NEPA and certification deadlines reduce time for thorough environmental and health reviews, raising the chance that impacts are inadequately assessed and mitigation is insufficient for affected communities and health systems.
Based on analysis of 5 sections of legislative text.
Directs the Army Corps to issue a nationwide permit for port dredging with fixed deadlines, narrows EPA/state disposal oversight, and amends Title 46 to exclude dredged material from a transport rule.
Official title: Require the Secretary of the Army, acting through the Chief of Engineers, to propose a new nationwide permit under the Federal Water Pollution Control Act for dredging projects, and for other purposes.
Introduced June 11, 2026 by Mike Lee · Last progress June 11, 2026
Creates a new, time‑limited nationwide permit (NWP) the Army Corps must propose, complete NEPA for, and issue to authorize Federal and non‑Federal dredging projects in U.S. navigable waters (including maintenance, expansion, or deepening up to 60 feet). The bill sets strict deadlines for Corps action, for state/interstate Clean Water Act section 401 certification decisions, and for Corps regional conditions; it limits EPA's 404(c) authority over disposal decisions made under the NWP and changes certain maritime statutory language to exclude dredged material from a transportation rule. Overall, the legislation fast‑tracks Corps permitting for port dredging, narrows or constrains some environmental review and oversight tools, and updates Title 46 to remove dredged material from specific transportation requirements.