((a)) ** In general** In conducting a feasibility study for a project (or a component of a project) for ecosystem restoration, the Secretary shall ensure that the recommended project includes, as an integral part of the project, a plan for monitoring the success of the ecosystem restoration.
((b)) ** Monitoring plan** The monitoring plan shall—
((1)) include a description of the monitoring activities to be carried out, the criteria for ecosystem restoration success, and the estimated cost and duration of the monitoring; and
((2)) specify that the monitoring shall continue until such time as the Secretary determines that the criteria for ecosystem restoration success will be met.
((c)) ** Cost share** For a period of 10 years from completion of construction of a project (or a component of a project) for ecosystem restoration, the Secretary shall consider the cost of carrying out the monitoring as a project cost. If the monitoring plan under subsection (b) requires monitoring beyond the 10-year period, the cost of monitoring shall be a non-Federal responsibility.
((d)) ** Inclusions** A monitoring plan under subsection (b) shall include a description of—
((1)) the types and number of restoration activities to be conducted;
((2)) the physical action to be undertaken to achieve the restoration objectives of the project;
((3)) the functions and values that will result from the restoration plan; and
((4)) a contingency plan for taking corrective actions in cases in which monitoring demonstrates that restoration measures are not achieving ecological success in accordance with criteria described in the monitoring plan.
((e)) ** Conclusion of operation and maintenance responsibility** The responsibility of a non-Federal interest for operation and maintenance of the nonstructural and nonmechanical elements of a project, or a component of a project, for ecosystem restoration shall cease 10 years after the date on which the Secretary makes a determination of success under subsection (b)(2).
((f)) ** Federal obligations** The Secretary is not responsible for the operation or maintenance of any components of a project with respect to which a non-Federal interest is released from obligations under subsection (e).